/
/
/
Construction of Water Conveyance Facility for the Bulacan Bulk Water Supply Project

Construction of Water Conveyance Facility for the Bulacan Bulk Water Supply Project

Marilao, Obando, Calumpit, Bulacan
Luzon Clean Water Development Corporation
January 30, 2017
April 15, 2019
Completed

Pipelaying of an 80 km pipeline consisting of 600mmø –
1,500mmø (Polyurethane lined and coated as per
AWWA C222 or epoxy-lined and coated as per
AWWA C210-70 Steel pipe), 400mmø – 500mmø
(Ductile Iron Pipe) and 300mmø (PVC Pipe) shall
be laid among the existing Quirino Highway, Tungkong Mangga – Muzon Road, Villarica – Marilao Road and towards Mac Arthur Highway from the junction at Obando to Calumpit.