[Completed] Road

ROAD, EXPRESSWAY, BRIDGE, DRAINAGE STRUCTURES, SLOPE PROTECTION AND FOOTBRIDGE CONSTRUCTION PROJECTS

 

 

 

TPLEX – Aloragat Waterway Bridge of Section 3A

Type of Work: Construction of Bridge and Underpass Structures

Owner: Private Infra Development Corporation (PIDC)

Date Started: August 14, 2015

Completion Date: November 21, 2016

 

 

Southern Tagalog Arterial Road (STAR) Project - Additional Works

Type of Work: Construction of Bridges, Asphalt Overlay, Rehabilitation of Asphalt Shoulder and PCC Pavement

Owner: STAR Infrastructure Development Corporation / San Miguel Corporation

Date Started: April 01, 2013

Completion Date: September 30, 2014

 

 

Contract Package CP1: Buray Junction to Brgy. Tinani, Samar and Eastern Samar

Type of Work: Construction / Rehabilitation of existing  roads & bridges that includes road widening, pavement, strengthening, improved drainage and traffic calming measures, slope protection structures.

Owner: Millennium Challenge Account - Philippines (MCA-P)

Date Started: October 5, 2012       

Completion Date: June 02, 2014

 

 

Construction of Dalton Pass Nueva Viscaya (New Alignment) (San Jose Aritao Road, Segment 5, Dalton Pass Section, Eastern Alternate Route) Nueva Viscaya

Type of Work: New Construction of Roads (L=16.430 km.), Construction of / Rehabilitation of three (3) bridges.

Owner: Department of Public Works and Highways (DPWH)

Date Started: November 13, 2012       

Completion Date: August 15, 2014

 

 

Construction of the SCTEX Interconnection and Entry Ramp (H-4) under Contract Package II-A

Type of Work: Construction of expressway.

Owner: Private Infra Development Corporation (PIDC)

Date Started:  October 01, 2012       

Completion Date: January 15, 2013

 

 

Contract Package II, Plaridel Bypass Road Under Arterial Road Bypass Project Phase I (Plaridel) 

Type of Work: Construction of PCCP, Construction of seven   (7)  bridges, drainage and slope protection works.

Owner: Department of Public Works and Highways

Date Started: May 4, 2011     

Completion Date: November 25, 2012

 

 

Construction of Tarlac – Pangasinan – La Union Expressway (TPLEX)

Type of Work: Construction of expressway, interchanges, overpasses, bridge, farm crossing, viaducts, and toll facilities

Owner: Private Infra Development Corporation (PIDC)

Date Started: December 8, 2010 

Completion Date: August 11, 2011

 

 

Development of Commonwealth Avenue From Philcoa to Batasan

Type of Work: Road widening, PCCP, concrete curb and gutter, drainage improvement works, supply and laying of RCPC, construction of  manhole without cover

Owner: Metropolitan Manila Development Authority (MMDA)

Date Started: November 17, 2009  

Completion Date: December 31, 2010

 

 

Rehabilitation of Surigao - Davao Coastal Road, Jct. Bacuag - Claver Section (Completion of Works)

Type of Work: Construction of PCCP, Earthworks, Drainage Structures & Slope Protection Structures

Owner: Department of Public Works and Highways (DPWH)

Date Started: November 05, 2007

Completion Date: July 31, 2009

 

 

Bohol Circumferential Road Improvement Project

Type of Work: Construction of PCCP with asphalt concrete overlay, rehabilitation and repair of 22 bridges, construction of RCBC and drainage structures, slope & shore.

Owner: Department of Public Works and Highways (DPWH)

Date Started: March 16, 2004

Completion Date: October 25, 2006 (2 months ahead)

 

 

Bongabon-Baler Road Improvement Project

Type of Work: Construction of five (5) bridges with a total length of 1,060 m; with 29 km PCCP, drainage structures and slope protection       

Owner: Department of Public Works and Highways (DPWH)

Date Started: October 22, 2003

Completion Date: Feb. 23, 2006 (2 months ahead)

 

 

Package 2B : EDSA LRT Line 3 Corridor (Mainline), EDSA (from Roxas Blvd. To Balintawak)

Type of Work: Construction of six (6) footbridges with total length of 787.38 m., one (1) Elevated Walkway, Loading and Unloading Bays, Pedestrian Steel Railings / See Thru Fence, Gantry Structures and Sidewalk / Geometric improvements.

Owner: Metropolitan Manila Development Authority (MMDA)

Date Started: November 15, 2007

Completion Date: May 07, 2009

 

 

Bicutan Interchange, Parañaque City

Type of Work: Construction of 500m. footbridge, road widening, provision of road signs & lane markings, curb and gutter, sidewalk, repair of existing street lights and landscaping

Owner: Metropolitan Manila Development Authority (MMDA)

Date Started: March 29, 2007

Completion Date: May 30, 2008

 

 

Construction of Pantal Bridge under Urgent Bridges Construction Project for Rural Development, Package III

Type of Work: Bridge Construction and Installation of Superstructure Steel Girder

Owner: Kawada  Industries, Inc. (Manila Branch)

Date Started:  July 01, 2007 

Completion Date: March 31, 2008

 

 

Construction of Daang Hari Extension Aguinaldo Highway – Coastal Road Section

Type of Work: Construction of PCCP, Earthworks, and Construction of drainage structures

Owner: Department of Public Works and Highways (DPWH)

Date Started: December 12, 2006 

Completion Date: May 20, 2007

 

 

Development of Commonwealth Avenue from Elliptical to Luzon Ave., Contract Package 1-I 

Type of Work: Construction of PCCP, Earthworks, and Construction of drainage structures

Owner: Department of Public Works and Highways (DPWH)

Date Started: December 12, 2006 

Completion Date: May 20, 2007

 

 

Construction of Aloragat Bridge and Approaches at Brgy. Cabanbanan, Manaoag, Pangasinan

Type of Work: Construction of Bridge with bored pile, installation of WBPI modular steel bridge superstructure, drainage and slope protection structures & construction of appurtenant structures

Owner: Department of Public Works and Highways (DPWH)

Date Started: November 17, 2006

Completion Date: October 25, 2007

 

 

Sixth Road – Project Bridge Component Contract Package M, Replacement of existing four (4) Bridges in La Union & Pangasinan

Type of Work: Construction of bridge and approaches with concrete pile cast-in drilled holes (Bored Piled)

Owner: Department of Public Works and Highways (DPWH)

Date Started: March 15, 2004   

Completion Date: March 30, 2005

 

 

Asphalt Overlay of Sta. Rosa-Cavite Boundary Road Km. 39 + 050 to Km. 45 + 750 (with exceptions)

Type of Work: Asphalting works

Owner: Department of Public Works and Highways (DPWH)

Date Started: April 13, 2004

Completion Date: August 05, 2004

 

 

Construction of Baliuag Flyover and Approaches along Cagayan Valley Road over Candaba-Baliuag and CVR Intersection, Baliuag, Bulacan

Type of Work: Construction of Flyover including its approaches, asphalting works, bored piling, pavement marking  

Owner: Department of Public Works and Highways (DPWH)

Date Started: November 14, 2003

Completion Date: April 28, 2004

 

 

Allacapan-Aritao Road Rehabilitation Project Phase II Contract Package VII-B, Construction of Bridges along Tumauini-Iguig Section, Cagayan Province

Type of Work: Construction of nine bridges, earthworks, subbase and base course, surface course, drainage and slope protection structures, miscellaneous structures.

Owner: Department of Public Works and Highways (DPWH)

Date Started: March 17, 2002

Completion Date: March 17, 2003

 

 

Sixth Road Project, ADB Loan No. 1473-PHI, Jexim Untied Loan Road Improvement Component, Group "A" Contract Package 6L-3, Infanta-Gen. Nakar Road, Quezon

Type of Work: Construction of bridge, road and ancillary works.

Owner: Department of Public Works and Highways (DPWH)

Date Started: February 28, 2000 

Completion Date: February 17, 2003 

 

 

Contract Package II with Supplemental Agreement No. 1 and No. 2, Rosario-Pugo Baguio - Baguio Road Rehabilitation Project

Type of Work: Construction of Road with Cement Treated base course, Bridge and Approaches and Slope Protection works  

Owner: Department of Public Works and Highways (DPWH)

Date Started: May 19, 1997

Completion Date: January 19, 2002

 

 

Bridge Retrofitting Program, (BRP) Contract Package J with S.A. No. 1, Magallanes, Ortigas and Pasig City

Type of Work: Seismic retrofitting works with installation of cable restrainers & concrete shear keys, non-seismic retrofit works & repair/replacement steel structural members  

Owner: Department of Public Works and Highways (DPWH)

Date Started: October 1999

Completion Date: August 2000

 

 

Bridge (Seismic) Retrofitting Program( BRP) Contract Agreement with Supplemental Agreement No. 1 & Contract Package 8A Construction of San Francisco Bridge Project, NCR and Tarlac  

Type of Work: Bridge construction with bored pile, Seismic Retrofitting w/ installation of cable restrainers & concrete shear keys, non-seismic retrofit works incl. repair/replacement of steel structural member, construction of slope protection works.

Owner: Department of Public Works and Highways (DPWH)

Date Started: November 16, 1995

Completion Date: May 24, 1997

 

 

Repair/Rehabilitation of MICT Wharf, North Harbor, Port of Manila

Type of Work: Concrete piling, reinforced girders, beams, slabs, retaining wall and repair of deteriorated piles by Fabric Jacket.

Owner: Philippine Ports Authority (PPA)

Date Started: October 05, 1994

Completion Date: February 28, 1997

 

 

Rehabilitation & Maintenance of Bridges along Arterial Roads Project, Phase I, Package IV Marilao Bridge, Marilao, Bulacan

Type of Work: Construction of bridge and approaches with concrete pile cast-in drilled holes (Bored Piled) in Pier 1 & 2

Owner: Department of Public Works and Highways (DPWH)

Date Started: July 01, 1996

Completion Date: November 10, 1996

 

 

Aritao-Sta. Rita Road Rehab. Proj. Seg. VI, and Including the rehab. of Putlan Bridge & Laoag-Allacapan Road Improvement Project

Type of Work: Construction of bridges, PCCP, RCPC, RCBC, slope protection, and construction of river structures such as spurdikes and revetment and Consultant's Office Building    

Owner: Department of Public Works and Highways (DPWH)

Date Started: July 08, 1994

Completion Date: October 28, 1996 (3 months ahead)

 

 

Repair/Rehabilitation of San Juanico Bridge, Samar, Leyte

Type of Work: Concreting of slab, repair of deteriorated piles by seal concrete jacket, asphalting of concrete surface and application of epoxy paint    

Owner: Department of Public Works and Highways (DPWH)

Date Started: June 01, 1996

Completion Date: September 30, 1996

 

 

Nagtahan-R. Magsaysay Blvd. Parallel Road Project and Construction of Bayan-Bayanan Outfall, Contract Package 2, Sta. Mesa, Manila and Marikina City

Type of Work: Construction of PCCP, streetlights, building & drainage outfall, concrete piling works  

Owner: Department of Public Works and Highways (DPWH)

Date Started: May 16, 1991

Completion Date: September 30, 1992 

 

 

 